What is Project Cost Estimation?
Project Cost
Estimation is defined as the process of approximating the total expenditure of
the project. The accuracy of the cost estimation and budgeting in project
management depends on the accuracy and details of the project scope, which is
the scope baseline. The scope will also define any constraints like date,
resources or budget. The risk register will help to calculate estimate types of
costs, the expenses made behind the contingent action and the expenses made to
cope with risks.
To estimate the cost
of project you have to categorize various cost types into categories like:
- Labor
cost
- Equipment
cost
- Cost
of supplies
- Travel
cost
- Training
cost
- Overhead
cost, etc.
Four Project Cost Estimation Techniques
How exactly project
managers completing a cost estimate depends upon a number of factors. Some
organizations, for example, require all projects to be budgeted for according
to very specific policies; others may defer to the expertise of the project
manager. Similarly, many organizations might work off of rough estimates in the
earliest stages of project planning compared to later stages where more exact
estimates are required.
Below, we explore
four of the most common cost estimation techniques that you can leverage.
1. Analogous
Estimating
Through analogous
estimating, a project manager calculates the expected costs of a
project-based upon the known costs associated with a similar project that was
completed in the past. This method of estimation relies upon a combination of
historical data and expert judgment of the project manager.
Because no two
projects are exactly the same, analogous estimating does have its limitations.
As such, it is often leveraged in the earliest stages of project planning, when
a rough estimate can suffice. Analogous estimating can also be used when there
is relatively little information about the current project available.
2. Parametric
Estimating
In parametric
estimating, historical data and statistical modeling are used to assign a
dollar value to certain project costs. This approach determines the underlying
unit cost for a particular component of a project and then sales that unit cost
as appropriate. It is much more accurate than analogous estimating but requires
more initial data to accurately assess costs.
Parametric estimating
is often used in construction. For example, an experienced construction manager
might understand that the typical new home will cost a certain number of
dollars per square foot (assuming a particular margin of error). If this
average cost, the margin of error, and the square footage of a new project are
known, then parametric estimating will allow them to identify a budget that
should accurately fall within this range. Other examples might include
estimating the cost per unit to print and bind a book or to build an electronic
device.
3. Bottom-Up
Estimating
In bottom-up
estimating, a larger project is broken down into a number of smaller
components. The project manager then estimates costs specifically for each of
these smaller work packages. For example, if a project includes work that will
be split between multiple departments within an organization, costs might be
split out by department. Once all costs have been estimated, they are tallied
into a single larger cost estimate for the project as a whole.
Because bottom-up
estimating allows a project manager to take a more granular look at individual
tasks within a project, this technique allows for a very accurate estimation
process.
4. Three-Point
Estimating
In three-point
estimating, a project manager identifies three separate estimates for the
costs associated with a project. The first point represents an “optimistic”
estimate, where work is done and funds spent most efficiently; the second point
represents the “pessimistic” estimate, where work is done and funds spent in
the least efficient manner; and the third point represents the “most likely” scenario,
which typically falls somewhere in the middle.
Three-point
estimating relies on a number of weighted formulas and originates from
the Program Analysis and Review Technique (PERT).
0 Comments